One PVBAT L2P G2 12kW / 12kVA split-phase hybrid inverter can be installed with one ELEPHANT-48628 battery cabinet in two ways: off-grid, or grid-connected backup. Both overviews show solar input on the inverter’s dual MPPT and an optional generator. This is an educational overview, not a construction or wiring diagram, and it is not a substitute for the product manuals. Installation must be performed by a licensed electrician.
These diagrams show typical U.S. connection overviews for one wall-mounted PVBAT L2P G2 12kW split-phase hybrid inverter and one ELEPHANT-48628 32.15kWh battery cabinet (51.2 V / 628 Ah LiFePO4). They are an educational overview only — not a construction or wiring diagram. Follow the L2P G2 user manual and the ELEPHANT-48628 user manual, and local code / the authority having jurisdiction (AHJ). Installation must be performed by a licensed electrician.
What stays the same in every option
- Both options use one ELEPHANT-48628 cabinet and one wall-mounted L2P G2 12kW / 12kVA inverter (120/240 Vac, dual MPPT).
- Battery DC cables use both 175A Anderson ports on the cabinet, with a 150 A maximum continuous current per port. The diagrams show an installer-supplied 2P-300A DC breaker / bus and 0 AWG / 54 mm² cable.
- Communication uses a straight-through RJ45 from CN17 on the ELEPHANT side panel to RS485/CAN port 8 on the L2P G2. Follow the manuals for protocol and pinout.
- Solar input, when used as shown, goes to PV1 and PV2 (dual MPPT, 6500 W × 2, MPPT voltage range 60–450 VDC, maximum PV open-circuit voltage 500 VDC). The diagrams show 6 mm² / 10 AWG PV cable and a 2P-25A breaker on each string. The installer must confirm that each string’s Voc stays at or below 500 VDC.
- Load output is shown from the inverter LOAD terminals as AC L1 / L2 / N, 13 mm² / 6 AWG, with a 3P-63A breaker.
- A generator connection is optional in both options, from the inverter GEN terminals, shown as AC L1 / L2 / N, 13 mm² / 6 AWG, with a 3P-63A breaker.
- PVBAT provides product specifications and installation guidance. PVBAT does not perform on-site electrical installation.
Option 1: Off-grid
This setup uses PV and the ELEPHANT-48628 cabinet to power the off-grid load through the L2P G2. No utility connection is used in this option. The inverter GRID / utility terminals are not used in this scenario.

The diagrams show one example array: nine panels in series on PV1 (MPPT 1) and nine panels in series on PV2 (MPPT 2). That is an example, not the only valid array. Confirm your panel Voc, current, and string design so each string stays within the L2P G2 limits, including a maximum PV open-circuit voltage of 500 VDC and the 60–450 VDC MPPT range.
Off-grid loads connect to the inverter LOAD terminals (AC L1 / L2 / N). An optional generator can connect to the GEN terminals. Because this option has no utility connection, the GRID terminals shown in the bottom-gland detail are left unused.
Option 2: Grid-connected backup
This setup connects the L2P G2 to the utility grid and uses the ELEPHANT-48628 cabinet for backup. Backup loads are fed from the inverter LOAD terminals. On-grid home loads stay on the grid side of the connection, with a CT shown on the grid path. The diagram notes a default CT direction toward the inverter.

Solar input uses the same dual-MPPT connection as Option 1, including the example of nine panels in series on each tracker, subject to the 500 VDC Voc limit. The GRID terminals are used in this option. A licensed electrician must design the utility interconnection, CT placement, and backup-load wiring to match the manuals, local code, and the utility or AHJ requirements. Do not treat this overview as a complete interconnection plan or a whole-home installation plan.
Ports used in these diagrams
| Connection | On the equipment | Role in these options |
|---|---|---|
| Battery DC + / − | ELEPHANT-48628 side-panel Anderson ports (175A); use both ports | Battery cables to the L2P G2, through an installer-supplied 2P-300A DC breaker / bus and 0 AWG / 54 mm² cable; 150 A max continuous per port |
| Communication | ELEPHANT CN17 (side panel) to L2P G2 RS485/CAN port 8 | Straight-through RJ45; follow the manuals for protocol and pinout |
| PV input | L2P G2 PV1 and PV2 (dual MPPT) | Solar input; 6500 W × 2, MPPT 60–450 VDC, maximum Voc 500 VDC. The diagrams show 6 mm² / 10 AWG cable, a 2P-25A breaker on each string, and an example of 9 panels in series per tracker |
| LOAD output | L2P G2 LOAD terminals, AC L1 / L2 / N | Off-grid load in Option 1; backup load in Option 2. Diagrams show 13 mm² / 6 AWG and a 3P-63A breaker |
| GRID / utility | L2P G2 GRID terminals, 120/240 Vac split-phase | Not used in Option 1. Used in Option 2 with a CT; the diagram notes a default CT direction toward the inverter |
| Generator (optional) | L2P G2 GEN terminals, AC L1 / L2 / N | Optional in both options. Diagrams show 13 mm² / 6 AWG and a 3P-63A breaker |
Wire sizes, breaker ratings, and the 9-panel series example are taken from these overview diagrams. A licensed electrician must confirm every conductor, overcurrent device, and string design against the manuals, the actual equipment, and local code.
FAQ
Can I install this system without solar panels?
These two overviews both show PV strings on MPPT 1 and MPPT 2. A no-solar layout is not shown on this page. If you need a design without solar, follow the L2P G2 and ELEPHANT-48628 user manuals and have a licensed electrician plan the connections.
Do I need a licensed electrician?
Yes. This installation involves a battery cabinet, a hybrid inverter, PV wiring, and, in Option 2, a utility interconnection. It is not a plug-in setup. Installation must be performed by a licensed electrician and must follow the manuals and local code / AHJ.
Can this system power a whole home?
Option 1 shows an off-grid load from the LOAD terminals. Option 2 shows backup loads from the LOAD terminals and on-grid home loads on the grid side. Whether a given home’s loads will run — and for how long — depends on those loads, startup surge, and available energy. Do not treat this overview as a whole-home installation plan.
What is the difference between the two options?
Option 1 is off-grid: there is no utility connection, and the GRID terminals are not used. Option 2 is grid-connected backup: the inverter connects to the 120/240 Vac split-phase grid with a CT, backup loads come from the LOAD terminals, and on-grid home loads stay on the grid side. Both options can include the dual-MPPT solar input shown in the diagrams and an optional generator.
What are the GRID terminals for?
In Option 2 they connect the L2P G2 to the utility grid, with a CT on the grid path. In Option 1 they are not used. Follow the manuals and the electrician’s interconnection design for CT placement and any utility requirements.
How should solar panels be configured?
Use the L2P G2 PV1 and PV2 inputs. Keep each string’s open-circuit voltage at or below 500 VDC, and within the 60–450 VDC MPPT range, with a maximum of 6500 W per tracker. The 9-panel series layout on each MPPT in the diagrams is one example, not the only valid array. Confirm your panel ratings and string design before installation.
Is a generator required?
No. A generator is optional in both diagrams. If you add one, a licensed electrician should connect it to the L2P G2 GEN terminals as shown in the manuals and the overview.
How is the battery communication wired?
The diagrams show a straight-through RJ45 from CN17 on the ELEPHANT-48628 side panel to RS485/CAN port 8 on the L2P G2. Follow both user manuals for protocol, pinout, and any required settings.
Next step
Review the ELEPHANT-48628 32.15kWh battery cabinet and the L2P G2 12kW split-phase hybrid inverter for specifications, and download the ELEPHANT-48628 user manual and the L2P G2 user manual before any installation. For a U.S. load review, use the product pages or the free solar design page.
Educational overview only — not a construction or wiring diagram, and not a substitute for the manuals. Installation must be performed by a licensed electrician. Follow the L2P G2 and ELEPHANT-48628 user manuals and local code / AHJ.